403 Keele Steet - Village by High Park – Project update

403 Keele Steet - Village by High Park artsist renderings
   Tower A (Phase 2)                           Tower B (Phase 1) 
403 Keele Steet - Village by High Park artsist renderings

 

 

Village by High Park is a high rise condominium development consisting of one 16 storey 296 unit condo and one 23 storey 311 unit.  Commercial retailspace will also be provided at ground level.

 Project update

·       September 2008 – Demolition was completed on the old Canadian Tire store

·       October 2008 – Shoring work to hold back the CP rail lines in progress

·       December 2008 – Continued on site preparation

·       January 2009 – Crane installed to begin Tower B (16 storey 296 unit)

 Looking forward

·       Spring 2009 - Crane is installed to begin Tower A (23 storey 311 unit)

·       Early Winter 2009 – Tower A and B external structure complete

·       Winter 2010 - Internal work to compete suites, amenities and HVAC

·       Spring/Summer 2010 – Occupancy begins!

 

Options for Homes is also hoping to hold a community celebration this spring

Submitted by Matrin L.