Bunge post 5 - 30 Weston Rd, Trinity Development

30 Weston Rd is a site of a large conversion development from industrial uses which were historically  stockyards related and more recently edible oil processing. This site is the last large land tract of this size  in the community to be developed from the former stock yards.  This blog hopes to follow this process as tightly as possible hence the reason for the multiple posts.

Today post concerns the removal of the gas feed from the utility lines into the property which is being removed today {Feb 12 2009}

[caption id="attachment_2728" align="aligncenter" width="300" caption="The work site north West Corner of St Clair Ave. and Weston Rd. viewof  grey metal manhole shoring wherein lies the main and feed pipe connection."]The work site north West Corner of St Calir Ave. and Weston Rd. view grey metal manhole shoring wherein lies the main and feed pipe connection[/caption]

[caption id="attachment_2729" align="aligncenter" width="350" caption="When the gas feed line is cut today the site will be severed from the gas network"]When the gas feed line is cut today the site will be severed from the gas network[/caption]

[caption id="attachment_2730" align="aligncenter" width="300" caption="Helpful hint image, if you ever have to close a large gas main this method of clamping down on the pipe with a powered clamp will stop about 98 percent of the gas from flowing through the pipe. The black wrap is a static electrical charge dissipater "]Helpful hint image, if you ever have to close a large gas main this method of clamping down on the pipe with a powered clamp will stop about 98 percent of the gas from flowing through the pipe. The black wrap is a static electrical charge dissipater  [/caption]