Answer to question about the fill material on the site or near it.

A1. To the City's knowledge, there is still a small amount of residual impacted fill material noted to exist below or adjacent to the remaining concrete rail bed in front of 40 Wabash Avenue that should be removed from the site as part of any future development work. The City will arrange and co-ordinate with an independent environmental consultant to provide environmental and inspection services, however, the prime consultant will be required to co-ordinate and implement any requirements of the investigation in the tender and contract documents. Based on the results of the Environmental Assessment Report, the details of further remediation or risk assessment strategies will be known.

 

Answer too too the question, Is it anticipated that the existing hardscape plaza square is to remain?

A2. The future of the existing hardscape plaza square will be determined during the investigation/program confirmation phases and the approach to schematic design.

Question about the Fieldhouse,  Is the Fieldhouse likely to remain in use if it is not repurposed as a part of the community centre?

A3 The future of the Fieldhouse and its use will be determined during the investigation/ program confirmation phases and the approach to schematic design.