For: Humber Bay Shores Park Trail Improvement Project, Phase 2
Scope of Work for this project includes, but is not limited to the following:
1. Site protection and multi-use trail traffic control detour signage, tree protection, sediment
control.
2. Removal of trees, asphalt paving, interlock paving, concrete edges, etc.; removal,
storage & protection of site furnishings, various park signs, post and rail fences, rock
stones, etc. for reuse.
3. Construction of a wider multi-use trail including asphalt, concrete and interlock paving; granular paving, concrete curbs, tactile warning plates; re-installation of removed & stored items, painted lines and markings, sod restoration, asphalt restoration in parking lot staging area, localized grading and drainage improvements including catch basins, manhole & drain pipes, retaining rocks, dry-laid natural stone walls, tree and shrub planting, shade structures, and site restoration, etc.
Please refer to the Request for Tender (RFT) document in your possession and be advised of the following:
1. SCHEDULE:
1.1 Update to Section 4 Scope of Work
Project area is available to start constructions: April 1, 2019
Construction to start no later than: April 1, 2019 Substantial Completion must be complete by: July 31, 2019 Final Completion: September 16, 2019
Subscribe to:
Post Comments (Atom)
Each and every day multiple hours I miss Matt and Nate
He’s really does not answer my questions about Matt and Nate, No way, they know the truth
-
[caption id="attachment_6078" align="aligncenter" width="473" caption="Looking out of the/one of the reta...
-
Starbucks to come to 3077 Dundas Street West? The old Handyman Shop, Junction Residents Association.A commenter on the blog has recently commented that the new building on the South East corner directly across from Crema may be housing a St...
-
The Handyman Shop is sold! This great looking building located on the corner of Dundas and Quebec is a favourite for many people in the Jun...
No comments:
Post a Comment