Wednesday, April 29, 2009
Bermingham has two roles in the West Toronto Diamond project
Bermingham Construction Ltd. is not only one of the contractors installing the piles at the West Toronto Diamond project, Bermingham Construction Ltd is closely related company to Berminghammer Foundation Equipment which manufactures the pile drivers being used on the project.
Bermingham created the manufacturing line of their business in the mid-1960s, to manufacture pile drivers to its own specifications, uses and sales to other foundation contractors.
...from the manufacturing side of company site...
Berminghammer Foundation Equipment is closely associated with Bermingham Construction Limited, a Canadian company with over ninety-five years of pile driving experience. Years of extensive research, development, and job performance testing with Berminghammer’s own pile driving crews have gone into the production of the only diesel pile hammer designed expressly for piling contractors.
Mark V Series Diesel Pile Hammers company page link
Labels:
Berminghammer Foundation Equipment,
Canadian Pacific Railway,
Carleton Village,
city planning,
Development,
Go Transit,
Metrolinx,
Mount Dennis,
Railways,
The Junction,
The Junction Develpment,
The Junction railroads,
Toronto,
Toronto West Diamond grade separation,
Ward 11 (York South-Weston},
Ward 13 (Parkdale-High Park),
Ward 14 – (Parkdale-High Park),
Ward 16 Eglinton-Lawrence,
West toronto,
West Toronto Diamond project
Subscribe to:
Post Comments (Atom)
Each and every day multiple hours I miss Matt and Nate
He’s really does not answer my questions about Matt and Nate, No way, they know the truth
No comments:
Post a Comment